Friday, August 19, 2011

Patience Comes to An End

Welcome back, friends!  In our last episode, the tentative twosome was attempting to negotiate their way through the treacherous currents of the city bureaucracies.  Guess what!  As with any good soap opera, the fact that you haven’t heard from us in while doesn’t mean you’ve missed anything – we’re still floundering right where you left us…

Last week began with a follow-up call to our new friend at HARC to see where we were with approvals.  We got sign-offs on a couple small things (painting the roof of the main house, and some exterior work to the little guest house).  However, there were issues with some other projects (what a surprise).  We had applied to remove some rotted exterior siding and to replace rotted sill beams on the main house.

Typical example of rotted siding (and bad plumbing).

Unfortunately, we didn’t specify HOW MUCH siding needed to be replaced – less than 15% of the total could get staff approval, but more than that would require an audience with the full HARC commission.  That was dopey enough, but the real kicker had to do with the sill beams.

In previous posts, we explained how everything had to be approved by HARC before going to the building department for permitting.  As ridiculous as it sounded to have to apply to replace something that is not visible from the street, we were told we had to get approval on the sills anyway to make sure we weren’t changing the height of the house.  After submitting the application, however, we were told it wasn’t acceptable because it hadn’t been approved by the building department.  Huh?  In a true dose of circular logic, we were being told that we couldn’t get a permit from the building department without HARC approval, which we couldn’t get without a permit from the building department!!

After Kevin cleared the phone of the bits of brain that had exploded out of my head during the conversation with HARC, I called the building department.  They said they could sign off on replacing small sections of sill, but if it was more than 4-6’, they’d need stamped engineering drawings.  Having thus decided to swallow that bitter pill, my next phone call was to our local consultant (a friend of Kevin’s folks).  He said his engineer would probably want to survey the existing sills first, so he recommended removing enough siding to expose the sill beams (probably 2 or 3 courses).  That’s right, clever reader – we have come full circle back to our original HARC problem of how much siding gets removed.

I did a rough sketch of where the siding was actually rotten, calculated what percentage of the total square footage of siding that was, tripled it (in case I found more), and came up with about 13%. I then decided (foolishly, it would turn out) to be as honest with HARC as possible.  We submitted a revised application explaining that we might need to REPLACE as much as 13% of the siding, but might need to REMOVE as much as 50% to do all the maintenance work required.  I was very clear that we would not be replacing 50% of the old siding, just removing it and putting it back.  This new application was met with a dour look, a shake of the head, and a “we’ll need to consider this” comment.  Disappointed by the lack of enthusiasm, but undaunted, I thought we were at least on the right track – this new application had been submitted early enough that it could make it to the next HARC commission meeting if necessary (we knew we couldn’t get it into the meeting last week, but at least it was in the pipeline for the next one).  In the meantime, we still had plenty of “surreptitious” work to do to the back cottage to keep us busy.  And the roof painting project had found its way to the next level with the building department (applying for the actual permit), so life was good.

Welcome to Kangaroo Court

Because we thought it might be possible we’d be summoned before the majesty of the full HARC commission at some point, we decided to observe a public session and see how it all works.  It doesn’t.  Of 14 items on the agenda, 9 were postponed until the next bi-weekly meeting, and one was flatly rejected.  One postponement was required because the triumvirate (there should have been 5, but 2 of the lords had been excused) needed more “documentation” as to why some rotten porch columns needed to be replaced.  The poor guy had already been banished once before (2 weeks prior) to investigate the possibility of salvaging the exteriors of the columns, replacing the interiors with steel, and re-wrapping the salvage over the steel.  He had discovered that they were too far gone, and came back with a comparable plan (with manufacturer’s drawings) to use steel columns, and then cover them with new wood (not fiberglas, plastic, or vinyl) that had been turned to exactly match the old columns.  The three monkeys, however, did not feel there was sufficient evidence that he couldn’t salvage the existing columns, so they sent him away to bring more proof.  I can only hope that next time he arrives with a wheelbarrow full of wood pulp and dumps it at their feet…  Another postponement was necessitated because one commissioner decided he had a conflict of interest, and recused himself on the spot.  The other two decided they did not alone constitute a quorum, so the applicant’s business was postponed for another two weeks!  They are sticklers for procedure, including an insistence that all business coming before them be presented two Fridays before the meeting.  They therefore should have known about the conflict well in advance, and they shouldn’t have “excused” anyone if it meant being unable to conduct the people’s business!!  Despite the foregoing, the most heinous of  their acts that day was in the rejection of an application.  For a change I won’t elaborate on the details (the evidence and testimony were very involved), but the gist is that they simply lied in the face of the facts.  As best we could surmise, there was a political component to this one application (a city commissioner even spoke about it), so the goon squad fabricated a reason to reject it.  It was absolutely astonishing to witness.  But at least we got a taste of how the system operates, and hopefully picked up a few tips on how to dazzle these buffoons with enough pomp and circumstance if our time comes.

The Work Continues

The floor tile arrived for the back cottage, so we continued prepping to lay tile while waiting for word on our other permits.  We also started re-routing plumbing to get the toilet and sinks where we want those drains before laying the floor. 

Cottage Bathroom plumbing ready.  Next steps are to close up walls and install the pocket door in the foreground.

It’s all necessary work, but I was getting antsy to deal with the real meat of this project – replacing the sills.  I called HARC early on Friday of last week (the deadline day to get applications submitted to get to the next commission meeting) to see if I could come to the office to talk through my siding application.

(Remember the circular logic: I need HARC to approve my application to get a permit from the building department to pull the siding to be able to have the engineer START the process of going to the building department to sign off on a plan to replace the sills that HARC can approve to get the building department to give me a permit to do the work.  If you need a drink, please get one now)

Anyway, the poor, overwhelmed darling started waving the red cape at me by saying she wasn’t taking any walk-ins that day and she hadn’t had a chance to review the application.  I charged.  I told her we weren’t delaying any longer.  I told her we needed to start, and I was already on my way over to take back the application, and re-submit it to take down less than 15% of the siding.  I told her that I had seen how the commission worked, and I was not waiting another 2 weeks to start.  She reluctantly caved (I think mostly to keep a raving lunatic out of her office), agreed to strike the 50% line, and signed off while I was on the phone.  Finally, our little application was moving to the building department…  Next stop, demolition!

That’s about all the energy I have to write for this episode, dear reader, and I suspect it’s about all the energy you can muster to have read it!  Join us again for future adventures, and remember how once upon a time you all thought we were going to be living the dream…

No comments: